Have a peek at the construction progress at Grand Pacific MarBrisa
Resort. Work is in full-swing here at Grand Pacific's largest
resort with two of our luxury villas now open and our ocean view
pool and gym area in the process of completion.
View our images below for a real impression from the spectacular
site of Grand Pacific MarBrisa Resort, and please come back for
further updates!
First Villas now open!
MarBrisa PROJECT PROGRESS UPDATE - May 15, 2010
|
|
|
Click on any thumbnail below to view a larger image.
|
|
|
|
| |
Construction of Villa 53
- Brown Coat Stucco is complete. Finish Color Coat to start Next Week
- Architectural Foam Shapes are 75% installed ands grouted.
- Gypcrete was poured in place on the 2nd and 3rd Floors.
- All Three Floors have been painted with three-coats.
- Carpet has been installed on the 1st Floor with Carpet installation starting on the 2nd Floor on 5/17.
- HVAC Systems are all ready to go with all the Finish Trim in place
- All Electrical Systems are installed pending the A/C condensers. Trim is 50% Complete.
- Plumbing Fixtures are being installed through out all floors.
- Kitchen & Bath Cabinets are installed on the 1st Floor & halfway on the 2nd Floor.
- Ceramic wall tile work is complete on 1st Floor. Ceramic Floor Tile starts next week.
- Frame and Door work starts next week.
- Best Possible Occupancy Date: 7/2/10 (No Rain)
|